ISP98, URDG 758 and UCP 600: which rules apply to each guarantee
The International Chamber of Commerce (ICC) publishes rules that banks and companies adopt all over the world. In plain words: they are private "rules of the game". They only apply when the wording of the guarantee or letter of credit expressly states which rules apply. Without that line in the wording, the matter is left to the law of the country.
ISP98: the rules for standby letters of credit (SBLC)
The International Standby Practices (ICC publication 590) were drafted specifically for SBLCs. They accept copies of documents, provide for automatic renewal (evergreen, a guarantee that renews itself), require a demand for payment and allow transfer only for the full amount.[1]
URDG 758: demand guarantees (BG)
The Uniform Rules for Demand Guarantees, in force since 2010, govern demand bank guarantees (BG). They have their own rules on issuance, independence, demand, reduction and termination.[2] "On first demand" means that the bank pays when the beneficiary makes a demand and presents the documents required by the wording, without debating the contract.
UCP 600: documentary credits
The Uniform Customs and Practice (UCP 600) govern commercial letters of credit, used to pay for a sale against shipping documents. They may be used for standbys "to the extent applicable", but are considered the least suitable rules for guarantees.[1][3]
Which rules to choose
- SBLC: ISP98.
- Demand bank guarantee (BG): URDG 758.
- Import or export letter of credit: UCP 600.
- Presentation via SWIFT: permitted by ISP98 under certain conditions. Under URDG 758, it must be authorized in the wording.[3]
Practical example: the same guarantee, two sets of rules
A trading company issues a US$ 3 million payment guarantee in favor of a producer. If the wording cites ISP98, the guarantee is an SBLC and the demand for payment follows ISP98. If it cites URDG 758, it is a demand guarantee and the process follows the URDG. The documents required, the time limits and the method of presentation may differ. That is why the rules line is one of the first things to check.
What to do in practice before signing
- Look in the wording for the sentence "this standby is subject to ISP98" or "URDG 758".
- Be wary of wording with no rules or with rules that do not exist.[4]
- Ask the bank to explain how the beneficiary must present the demand for payment and within what time limit.
- Agree with your advisor on the language and place of presentation.
ISP98, URDG 758 and UCP 600 side by side
- Purpose: ISP98 covers standbys; URDG 758 covers demand guarantees; UCP 600 covers documentary credits.[1][2]
- Who uses them: ISP98 and URDG 758 protect the beneficiary against non-payment or non-performance; UCP 600 is the way to pay for a sale against documents.
- When they apply: only if the wording says they apply.
If you are the beneficiary, the rules define how to claim. If you are the party requesting the guarantee, the rules define what the bank may refuse. In both cases, read the wording before signing and ask the issuing bank to confirm the chosen rules.
How this topic connects with verification
The rules written into the wording also help to verify the guarantee. If the SBLC cites rules that do not exist, it is a warning sign. See the page "How to verify an SBLC".[4]
Frequently asked questions
Is ISP98 law?
No. It is a set of private ICC rules that applies when the wording of the guarantee incorporates it.[1]
Does URDG 758 apply to an SBLC?
It can be chosen, but the rules designed for SBLCs are ISP98.[5]
What does UCP 600 govern?
Commercial letters of credit (documentary credits), used to pay for sales against documents.[1]
Can a guarantee cite more than one set of rules?
The wording should state one clear set of rules. Two different sets create uncertainty; ask the bank to clarify before accepting.[3]
Where can I see the rules applied to my guarantee?
In the issuance message itself (MT760) and in the wording of the guarantee, both of which should cite the chosen rules.[3]